City inspectors and mechanical engineers get a clean, self-contained package: pass/variance CFM schedules, custom-annotated M-sheet plan atlases, and photographic rooftop verification.
| Marker ID | System / Zone | Drawing Tag | Design CFM | Actual CFM | Variance | Status |
|---|---|---|---|---|---|---|
| M1-A-K1 | Cookline Make-Up Air (MUA-1) | 16x16 / 10" Neck | 1,175 | 1,148 | -2.3% | PASS |
| M1-A-K2 | Cookline Make-Up Air (MUA-1) | 16x16 / 10" Neck | 1,175 | 1,210 | +3.0% | PASS |
| M1-A-S1 | Kitchen Zone Supply (FC-1) | CD-1 / 12" Neck | 620 | 628 | +1.3% | PASS |
| M1-A-S17 | Main Dining / Market Zone | CD-1 / 12" Neck | 625 | 612 | -2.1% | PASS |
| M1-A-S20 | High-Volume Supply Terminal | CD-2 / 16" Neck | 1,233 | 1,245 | +1.0% | PASS |
Upload your mechanical drawings (M-sheets), specifications, or equipment schedules. We typically turn around fixed-fee TAB quotes within 2 to 4 business hours.
Thank you! Your project information and plan details have been received. Our estimating team is reviewing your scope and will contact you promptly.